EVN will put into operation nine electricity projects with a total capacity of 2,696 MW.
Accordingly, turbines of the Plêikrông hydro-power plant are expected to start working in March and May, Sê San 4 in August, October and December; Buôn Kuốp in March and June; Buôn Tua Srah in August; Sông Ba Hạ in February and April; Bản Vẽ in December.
Three thermo-electricity plants will make their debut, Hải Phòng I in September and December, Quảng Ninh I in July and December, and Ô Môn I in February.
In addition, EVN has urged general contractors to restart the expanded Uông Bí I in March.
The group is also trying to inaugurate four coal-fueled power plants with a combined capacity of 3,800 MW, namely Nghi Sơn I in September, Mông Dương I in November, Duyên Hải I in September and Vĩnh Tân 2 in October.