• An Giang
  • Binh Duong
  • Binh Phuoc
  • Binh Thuan
  • Binh Dinh
  • Bac Lieu
  • Bac Giang
  • Bac Kan
  • Bac Ninh
  • Ben Tre
  • Cao Bang
  • Ca Mau
  • Can Tho
  • Dien Bien
  • Da Nang
  • Da Lat
  • Dak Lak
  • Dak Nong
  • Dong Nai
  • Dong Thap
  • Gia Lai
  • Ha Noi
  • Ho Chi Minh
  • Ha Giang
  • Ha Nam
  • Ha Tinh
  • Hoa Binh
  • Hung Yen
  • Hai Duong
  • Hai Phong
  • Hau Giang
  • Khanh Hoa
  • Kien Giang
  • Kon Tum
  • Lai Chau
  • Long An
  • Lao Cai
  • Lam Dong
  • Lang Son
  • Nam Dinh
  • Nghe An
  • Ninh Binh
  • Ninh Thuan
  • Phu Tho
  • Phu Yen
  • Quang Binh
  • Quang Nam
  • Quang Ngai
  • Quang Ninh
  • Quang Tri
  • Soc Trang
  • Son La
  • Thanh Hoa
  • Thai Binh
  • Thai Nguyen
  • Thua Thien Hue
  • Tien Giang
  • Tra Vinh
  • Tuyen Quang
  • Tay Ninh
  • Vinh Long
  • Vinh Phuc
  • Vung Tau
  • Yen Bai

VN to have eight nuclear power plants in next 20 years

VGP – By the year of 2030, Việt Nam will have built eight nuclear power plants to meet its current skyrocketing electricity demand.

June 23, 2010 10:45 AM GMT+7

This is part of PM Nguyễn Tấn Dũng’s newly-inked decision outlining key directions for the development of nuclear power until 2030.

Việt Nam is following a consistent policy to develop nuclear power for peaceful purposes and in favor of safety for people and environment.

Việt Nam follows consistent policy to develop nuclear power plant for peaceful purposes – Illustration photo

Three evolution phases

The development of nuclear power is divided into three phases.

The first phase (by 2015) aims at completing the approval of investment project, selecting location and contractors, and training the human resource for the construction of the first nuclear power plant.

Mechanisms and policies on forming and boosting the engagement of domestic players in equipment and material provision, construction, installation, project management, supervision and quality control plant will also be issued.

In the next five year stage, the first turbine of the Ninh Thuận Nuclear Power Plant 1 will be finished and put into operation by 2020. The second plant will also be built during this period.

For the last phase until 2030, next nuclear power plants will continue to be built, making nuclear power the country’s main energy.

During this period, Việt Nam targets to master the technologies of designing nuclear power plants and to raise domestic enterprises’ share up to 30%-40% in each nuclear power project.

List of nuclear power turbines to come into operation by 2030

No

Name of nuclear power plant

Capacity (MW)

Year of operation

1

First turbine of Phước Dinh Nuclear Power Plant

1,000

2020

2

Second turbine of Phước Dinh Nuclear Power Plant

1,000

2021

3

First turbine of Vĩnh Hải Nuclear Power Plant

1,000

2021

4

Second turbine of Vĩnh Hải Nuclear Power Plant

1,000

2022

5

Third turbine of Phước Dinh Nuclear Power Plant

1,000

2023

6

Fourth turbine of Phước Dinh Nuclear Power Plant

1,000

2024

7

Third turbine of Vĩnh Hải Nuclear Power Plant

1,000

2024

8

Fourth turbine of Vĩnh Hải Nuclear Power Plant

1,000

2025

9

First and second turbines of Central Nuclear Power Plant

2 x 1,000

2026

10

Third turbine of Central Nuclear Power Plant

1,300 – 1,500

2027

11

Fourth turbine of Central Nuclear Power Plant

1,300 – 1,500

2028

12

Fifth turbine of Central Nuclear Power Plant

1,300 – 1,500

2029

13

Sixth turbine of Central Nuclear Power Plant

1,300 – 1,500

2030

 

Total capacity

15,000 – 16,000

 

By Hải Minh