• An Giang
  • Binh Duong
  • Binh Phuoc
  • Binh Thuan
  • Binh Dinh
  • Bac Lieu
  • Bac Giang
  • Bac Kan
  • Bac Ninh
  • Ben Tre
  • Cao Bang
  • Ca Mau
  • Can Tho
  • Dien Bien
  • Da Nang
  • Da Lat
  • Dak Lak
  • Dak Nong
  • Dong Nai
  • Dong Thap
  • Gia Lai
  • Ha Noi
  • Ho Chi Minh
  • Ha Giang
  • Ha Nam
  • Ha Tinh
  • Hoa Binh
  • Hung Yen
  • Hai Duong
  • Hai Phong
  • Hau Giang
  • Khanh Hoa
  • Kien Giang
  • Kon Tum
  • Lai Chau
  • Long An
  • Lao Cai
  • Lam Dong
  • Lang Son
  • Nam Dinh
  • Nghe An
  • Ninh Binh
  • Ninh Thuan
  • Phu Tho
  • Phu Yen
  • Quang Binh
  • Quang Nam
  • Quang Ngai
  • Quang Ninh
  • Quang Tri
  • Soc Trang
  • Son La
  • Thanh Hoa
  • Thai Binh
  • Thai Nguyen
  • Thua Thien Hue
  • Tien Giang
  • Tra Vinh
  • Tuyen Quang
  • Tay Ninh
  • Vinh Long
  • Vinh Phuc
  • Vung Tau
  • Yen Bai

Gov’t demands faster site clearance of key transport projects

VGP – Prime Minister Nguyen Xuan Phuc has ordered the Ministry of Transport to accelerate site clearance of several key transport projects, including the eastern north-south expressway, so as to start construction of these projects as scheduled.

September 16, 2020 6:57 PM GMT+7

Other mega projects include Long Thanh International Airport, My Thuan-Can Tho expressway, and Ben Luc-Long Thanh expressway.

The eastern north-south expressway, which is of national priority for investment in the 2017-2020 period, is divided into 11 sub-projects with a total length of 654 kilometers running through 13 provinces and cities.

By the end of August, the relevant localities have completed 91.1% of site clearance work but the remaining volume requires drastic efforts so that it could be finished in the third quarter this year as ordered by the Government.

In addition, construction of resettlement areas has failed to meet the requirements, with only around 44% completed to date.

Meanwhile, the Government urged the People’s Committee of Dong Nai Province to quicken site clearance on 1,810ha for the first construction phase of the Long Thanh International Airport.

To build the airport, more than 5,000ha of land must be cleared and another 364ha are required to build the two resettlement sites.

Some 4,800 households and 26 organizations are expected to be relocated. Around 70% of the 15,500 people who will have to move are farmers, and the rest are rubber plantation workers and workers in other sectors.

This year, the Ministry of Transport is assigned to disburse around US$1.63 billion for key transport projects. The disbursement rate reached 33.7% compared to the national average figure of 30.2%.

Accelerating disbursement of public investment capital is considered a key solution of the Government to boost growth amid COVID-19 pandemic.